In brief
There is no single day when it flips. In England, a building meant to stay more than 28 days usually needs Building Regulations approval unless another Schedule 2 exemption covers it. Planning looks at the end date in any temporary permission. If a building stays without permission, councils have ten years to act for breaches completed since 25 April 2024.
On this page
Ask a supplier how long a temporary building can stay up and you may hear “as long as you like”. Structurally that can be true, since a well-made steel frame can stand for many years. But “temporary” in the rules is about time and purpose, and different rules draw the line in different places.
This post goes through the three time limits that matter in England, so you know when a “temporary” building starts to be treated like a permanent one.
There is no single switch-over date
It would be simpler if the law said “after X months a temporary building is permanent”. It doesn’t. Instead, three separate sets of rules each ask their own question:
- Building Regulations ask whether the building is meant to stay more than 28 days.
- Planning asks whether the building has permission, and for how long.
- Enforcement asks how long a council has to act if it doesn’t.
A building can be “temporary” for one of these and not for another, which is where people get caught out.
The 28-day line in Building Regulations
The Building Regulations 2010 exempt temporary buildings, and they define a temporary building as one not intended to remain where it is erected for more than 28 days.
That is a short window. A marquee for a weekend event can sit inside it. A storage building for a peak season, or a hall for a school term, cannot. Once a building is meant to stay longer than 28 days, it usually needs Building Regulations approval like any other new building, unless another exemption in Schedule 2 covers it.
Notice the word “intended”. The test is what you plan at the start, not what happens to occur. If you know the building is staying for six months, the exemption doesn’t apply from day one.
The end date in a temporary planning permission
Most temporary buildings that are not tied to construction work need planning permission, and councils can grant it for a limited period. The permission then carries a condition that the building must be removed by a set date.
Until that date, the building is lawful. After it, keeping the building is a breach of the condition. In practice this is the date that matters most for buyers, so put it in your diary and in the hire agreement.
If the need runs on, apply to extend or renew the permission before the date passes. Councils look at a renewal on its merits, so do not assume a second period will be granted.
The construction-work right in Part 4, Class A works in a similar way, except the end point is the end of the building work rather than a date. When the work is done, the building has to go.
Ten years: the enforcement limit
What if a building stays without permission at all? Councils can take enforcement action against unauthorised development, but only within a time limit.
For operational development in England this used to be four years. For breaches substantially completed on or after 25 April 2024, it is ten years, following the Levelling-up and Regeneration Act 2023, as set out in GOV.UK’s enforcement guidance.
In other words, leaving a building up and hoping nobody notices is a poor plan. Ten years is longer than most temporary buildings are needed for in the first place.
The three limits side by side
The table puts the three tests together.
| Rule | The question | Where the line falls |
|---|---|---|
| Building Regulations exemption | Is it meant to stay more than 28 days? | 28 days |
| Temporary planning permission | What date does the condition set? | The date in your permission |
| Construction-work right (Class A) | Is the building work finished? | The end of the work |
| Enforcement time limit | How long can the council act? | Ten years, for breaches completed since 25 April 2024 |
A worked example
Picture a logistics firm that hires a steel-framed building for “about six months” to hold overflow stock over a busy season. Six months is well past 28 days, so the building will usually need Building Regulations approval from the start. There is no construction work on the site, so the firm applies for planning permission for twelve months to leave some slack.
Trade stays high, and at month ten the firm sees it needs the building for another year. The right move is to apply to extend the permission now, and to agree an extended hire term, rather than letting the date slide past.
If temporary turns into permanent
Sometimes a building proves so useful that you want to keep it for good. That is a reasonable outcome, but it means a fresh look:
- Planning for permanent use, judged as any permanent building would be.
- Ownership, since a hired building may need to be bought. Our buying page covers what to check.
- Design checks for the longer life, including wind and snow on the roof.
It is far easier to plan this than to discover it at the end date.