In brief
Usually, if they stay more than 28 days. In England the Building Regulations 2010 exempt a temporary building, meaning one not intended to stay where it is put for more than 28 days. Beyond that, approval is usually needed unless another Schedule 2 exemption covers the building. Agree with the supplier who applies.
On this page
If a building comes on a lorry and leaves on one, surely the rules for permanent buildings don’t apply? That is what a lot of buyers expect, and for a short event they may be right. For anything longer, a temporary building in England is usually treated much like any other.
This post explains the 28-day exemption, what Building Regulations approval means for a temporary building, and the questions to settle with your supplier. It covers England. The other UK nations have their own building standards.
The 28-day exemption
Schedule 2 to the Building Regulations 2010 lists buildings that are exempt. One class covers temporary buildings, and it defines them tightly: a building not intended to remain where it is erected for more than 28 days.
So the exemption is about the plan, not the type of building. The same steel frame can be exempt for a three-week event and need approval when it goes up for a season.
Why most temporary buildings need approval
Think about how long buildings are usually wanted for:
- Peak storage tends to run for months.
- Decant space during a refit runs for the length of the works.
- School halls are usually needed for at least a term.
Every one of those is beyond 28 days. In other words, the temporary building exemption is for events and very short jobs. Longer stays usually need approval, unless another class in Schedule 2 covers the building, so check that list with the supplier or building control.
What approval looks at
Building Regulations are about how a building performs: that it stands up, that people can get out in a fire, and that it is safe to use. For a temporary steel building, the questions that come up most are:
- Structure: the frame and fixings must be designed for the loads on your site, including wind and snow if it stays through winter.
- Fire safety: escape routes, exits and the spread of fire.
- Use by people: access and, where people work inside, things like ventilation.
The IStructE guidance on temporary demountable structures is a useful reference on the structural side, whether or not your building ends up needing approval.
Who applies
Who applies is something to settle between you and the supplier. Suppliers of steel buildings often prepare the drawings and calculations and may make the application. It is very important to agree this in writing before you sign.
The questions to ask each supplier are simple:
| Question | Why it matters |
|---|---|
| Who makes the Building Regulations application? | So it is not left undone. |
| Is the fee in your price? | Quotes can look cheaper if it is left out. |
| What drawings and calculations do you provide? | Building control will want to see them. |
| Who deals with the base or ground fixings? | They are part of the structure. |
Ask the same questions of every supplier so the quotes compare like with like.
Planning is a separate question
Building Regulations approval does not give planning permission, and planning permission does not give Building Regulations approval. A building can need one, both or neither. Our post on planning permission for temporary buildings covers the planning side.
Two other duties that come with the building
Approval is not the end of the paperwork. Two other sets of rules apply whatever the Building Regulations position:
- Fire risk assessment. Under the Regulatory Reform (Fire Safety) Order 2005, the responsible person for non-domestic premises must carry out a fire risk assessment. A temporary building on your premises is part of it.
- CDM 2015. Putting up a large frame is a construction project, and a business client has duties. The HSE guidance for commercial clients explains them, including when a project must be notified: over 30 working days with more than 20 workers at any one time, or more than 500 person-days.
These apply to short and long buildings alike.
A worked example
An estates manager needs a hall for dining while the school kitchen and dining room are rebuilt over the autumn term. That is roughly 14 weeks, far beyond 28 days, so the hall will usually need Building Regulations approval unless another Schedule 2 exemption covers it.
The supplier’s quote says it will provide the structural calculations and drawings, and the school’s project manager arranges the application. The fire risk assessment for the hall is done before pupils use it, and exits are agreed with the supplier at design stage rather than after the frame is up.
When you are ready to compare suppliers on the same spec, our spec planner writes a short summary you can send with each enquiry.